← All CFM Flashcard Decks

Project Management & Execution Flashcards

7 cards from real CFM practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Project Management & Execution flashcards as text
  1. Which practice best supports version control when several analysts work on the same model?

    Answer: Using a consistent naming convention with version numbers and a change log of dates, authors, and edits

    Structured version naming plus a change log provides traceability and prevents lost or conflicting edits.

  2. Why should a model review be done by someone other than the model builder?

    Answer: An independent reviewer is more likely to catch logic errors and wrong assumptions the builder overlooks

    Independent (four-eyes) review removes the builder's familiarity bias and improves error detection.

  3. A modeler builds a simple skeleton showing the sheet flow and key output layouts and gets stakeholder feedback before building detailed calculations. What approach is this?

    Answer: Iterative prototyping

    Prototyping confirms structure and outputs early, so major redesigns happen when they are still cheap.

  4. Task X has 3 days of float. What does this mean?

    Answer: Task X can be delayed up to 3 days without delaying the project's completion

    Float (slack) is the amount a non-critical task can slip without pushing back the project end date.

  5. When is the best time to get formal stakeholder sign-off on the assumptions book?

    Answer: Before final outputs are produced, so results rest on agreed inputs

    Agreeing assumptions early avoids rework and disputes once outputs depend on them.

  6. Using PERT, a model build task has optimistic 2 days, most likely 5 days, and pessimistic 14 days. What is the expected duration?

    Answer: 6 days

    PERT expected time = (O + 4M + P) / 6 = (2 + 20 + 14) / 6 = 6 days.

  7. Which item is LEAST essential in a model handover package to a client's finance team?

    Answer: The builder's personal timesheet records for the project

    Handover should allow users to operate and maintain the model; internal timesheets do not serve that purpose.

Written and edited by , founder of Practice Test Geeks, with AI assistance. Exam facts are checked against the official sources linked below. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. fminstitute.com — Test delivery, exam dates, exam format, time limit, retake policy, score validity, registration deadline, retake fee, eligibility, fees · verified Nov 2026