Project Finance Modeling Flashcards
7 cards from real CFM practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Project Finance Modeling flashcards as text
Why is equity IRR usually higher than project IRR in a leveraged project?
Answer: Debt costs less than the project's return, so leverage magnifies equity returns
When the cost of debt is below the project's unlevered return, gearing boosts the return on the smaller equity investment.
Project (unlevered) IRR is calculated using which cash flows?
Answer: Pre-financing cash flows: capex outflows and post-tax operating cash flows, ignoring debt
Project IRR measures the asset's return regardless of how it is financed, so all debt flows are left out.
A 'dividend trap' in a project finance model occurs when:
Answer: Cash is available but negative retained earnings legally prevent dividend payments
Large early depreciation can cause accounting losses that block dividends even when the project has cash, so shareholder loans are often used to get around this.
Which tool is commonly used to find the breakeven opex increase at which minimum DSCR falls to 1.00x?
Answer: Goal Seek (or a macro) targeting minimum DSCR = 1.00x by changing an opex sensitivity input
Breakeven analysis solves for the input value that drives a chosen output, here minimum DSCR, to a critical threshold.
A six-month delay to the commercial operation date (COD) would most likely cause which combination of effects?
Answer: Higher IDC and fees, lost early revenue, and possibly delay liquidated damages received
Delay extends construction financing costs and defers revenue, which is partly offset by any delay LDs from the contractor.
The weighted average life of a project finance loan is calculated as:
Answer: The sum of each principal repayment times its time from drawdown, divided by total principal
Average life weights each principal repayment by when it occurs, so it shows how long the debt is outstanding on average.
In a well-built project finance model, an 'operations flag' for each period is typically:
Answer: 1 if the period falls between COD and the end of operations, otherwise 0
Timing flags are binary 1/0 switches driven by dates, which are multiplied into calculations to turn them on in the right periods.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- fminstitute.com — Test delivery, exam dates, exam format, time limit, retake policy, score validity, registration deadline, retake fee, eligibility, fees · verified Nov 2026