  1. Why does capitalized interest during construction (IDC) often create a circular reference in a project finance model?

    Answer: IDC increases total funding needs, which increases debt drawn, which increases IDC

    Funding IDC with debt raises the debt balance, which raises interest, creating a loop in the funding calculation.

  2. Which method is generally preferred by modeling best practice to resolve financing circularities?

    Answer: A copy-paste macro or closed-form algebraic solution instead of iterative calculation

    Copy-paste macros or algebraic solutions avoid the instability and hidden errors that iterative calculation can cause.

  3. A commitment fee on a construction loan facility is typically charged on:

    Answer: The undrawn portion of the committed facility

    Commitment fees pay lenders for keeping undrawn funds available and are applied to the undrawn balance.

  4. Under an 'equity first' construction funding structure, how are construction costs funded?

    Answer: Equity is fully contributed before any senior debt is drawn

    With equity first, sponsors put in their whole equity commitment before lenders fund, which lowers lender risk.

  5. An arrangement (upfront) fee of 2% on a $200m senior facility is usually modeled as:

    Answer: $4m paid at financial close and included in funding uses

    Upfront fees are a one-off cost at financial close based on total facility size and are funded as part of construction uses.

  6. A Debt Service Reserve Account (DSRA) is commonly sized to hold:

    Answer: About six months of upcoming senior debt service

    A typical DSRA covers the next six months of senior debt service, which protects lenders against short-term cash shortfalls.

  7. Under pro-rata funding with a 75:25 debt-to-equity ratio, how is $8m of construction cost in a period funded?

    Answer: $6m debt and $2m equity

    Pro-rata funding splits each period's costs at the target gearing: 75% x 8 = 6 debt and 25% x 8 = 2 equity.

Written and edited by , founder of Practice Test Geeks, with AI assistance. Exam facts are checked against the official sources linked below. Editorial policy