A facility manager is overseeing a HVAC replacement project that has fallen two weeks behind schedule. Which project management tool best helps identify which tasks must be accelerated to recover the overall timeline?
-
A
Gantt chart
-
B
Critical path method (CPM) analysis
-
C
Work breakdown structure (WBS)
-
D
RACI matrix