A bride requests 200 centerpieces but your studio can realistically produce 150 in the available time. What is the BEST project management response?
-
A
Accept the order and hope to find extra help last minute
-
B
Decline the order entirely without negotiation
-
C
Discuss a realistic scope with the client and potentially bring in a subcontractor
-
D
Agree to 200 and reduce quality to meet the volume