A contractor fails to deliver on the required delivery date but argues the delay was excusable. Which of the following qualifies as an excusable delay under FAR 52.249-14?
-
A
A subcontractor's bankruptcy caused by poor management
-
B
An unforeseeable fire destroying contractor facilities
-
C
Higher-than-expected material costs
-
D
Key personnel departing for a competitor