CFCM Contract Administration & Performance Management 5 — Questions and Answers
Question 1: A contractor fails to deliver on the required delivery date but argues the delay was excusable. Which of the following qualifies as an excusable delay under FAR 52.249-14?
- A subcontractor's bankruptcy caused by poor management
- An unforeseeable fire destroying contractor facilities (Correct answer)
- Higher-than-expected material costs
- Key personnel departing for a competitor
Correct answer: An unforeseeable fire destroying contractor facilities
FAR 52.249-14 recognizes acts of God, fires, floods, and similar unforeseeable events beyond the contractor's control as excusable causes of delay.
Question 2: Which document establishes the baseline for measuring contractor cost and schedule performance under an EVM system?
- The Work Breakdown Structure (WBS) dictionary
- The Performance Measurement Baseline (PMB) (Correct answer)
- The Integrated Master Schedule (IMS)
- The Contract Data Requirements List (CDRL)
Correct answer: The Performance Measurement Baseline (PMB)
The Performance Measurement Baseline (PMB) is the time-phased budget against which contract performance is measured in an EVM system.
Question 3: Under FAR 32.703-1, a fixed-price contract may be funded in increments. What is this funding approach called?
- Incremental funding (Correct answer)
- Severable service funding
- Advance payment authorization
- Provisional payment arrangement
Correct answer: Incremental funding
Incremental funding allows the government to obligate funds in stages on multi-year fixed-price contracts, provided the contract complies with applicable appropriations law.
Question 4: What is the contracting officer's primary responsibility when a contractor submits a certified cost or pricing data claim that later proves to contain defective data?
- Refer the matter to the Inspector General for criminal investigation
- Reduce the contract price by the overstatement amount plus interest (Correct answer)
- Immediately terminate the contract for default
- Issue a cure notice requiring corrected data within 10 days
Correct answer: Reduce the contract price by the overstatement amount plus interest
Under FAR 15.407-1 and the Truth in Negotiations Act (TINA), the government is entitled to a price reduction equal to the overstatement caused by defective cost or pricing data, plus interest.
Question 5: Which DFARS clause requires DoD contractors to report cybersecurity incidents affecting covered contractor information systems within 72 hours?
- DFARS 252.204-7009
- DFARS 252.204-7012 (Correct answer)
- DFARS 252.215-7007
- DFARS 252.246-7003
Correct answer: DFARS 252.204-7012
DFARS 252.204-7012 (Safeguarding Covered Defense Information) requires contractors to report cyber incidents affecting covered systems within 72 hours of discovery.
Question 6: Under FAR Part 49, which type of termination settlement agreement reimburses the contractor for costs plus a profit on work performed, without negotiating a final price?
- No-cost settlement agreement
- Vouchering settlement (Correct answer)
- Partial termination settlement
- Settlement by determination
Correct answer: Vouchering settlement
A vouchering settlement allows the contractor to submit vouchers for allowable costs plus a negotiated profit rate without fixing a final contract price.
Question 7: When a subcontractor performs defective work on a prime contract, which party bears direct liability to the government for contract non-conformance?
- The subcontractor, because they performed the work
- The prime contractor, because it is responsible for all contract performance (Correct answer)
- Both parties jointly and severally under the Contract Disputes Act
- The government must pursue DCMA to resolve subcontractor issues
Correct answer: The prime contractor, because it is responsible for all contract performance
The prime contractor retains full responsibility for all work performed under the prime contract, including work performed by subcontractors.
A contractor fails to deliver on the required delivery date but argues the delay was excusable.
Which of the following qualifies as an excusable delay under FAR 52.249-14?