  1. Under FAR 32.5, which type of contract financing allows the government to make payments to a contractor based on costs incurred prior to delivery of the end item?

    Answer: Progress payments based on costs

    Progress payments based on costs (FAR 32.5) are the most common form of financing where the government pays a percentage of allowable costs incurred before delivery.

  2. The standard progress payment rate for large businesses under FAR 32.501-1 is:

    Answer: 80%

    FAR 32.501-1 establishes 80% as the customary progress payment rate for large businesses based on total costs incurred.

  3. Under the Prompt Payment Act, what is the standard payment due date for supplies and services if no other date is specified in the contract?

    Answer: 30 days after receipt of a proper invoice

    The Prompt Payment Act establishes 30 days as the standard payment due date for most federal contracts when no other date is specified.

  4. Performance-based payments (PBPs) differ from progress payments primarily because PBPs are:

    Answer: Tied to the achievement of defined performance events or criteria

    Performance-based payments are financing payments tied to the accomplishment of specific performance events or criteria, not costs incurred.

  5. Under FAR 32.4, advance payments are considered the least preferred method of contract financing because they:

    Answer: Represent the greatest risk of loss to the government

    Advance payments carry the greatest risk to the government because funds are disbursed before any work is performed or costs incurred.

  6. A contractor's request for a progress payment must be supported by a certification that costs included are:

    Answer: Allowable, allocable, and reasonable

    Progress payment requests require certification that all costs are allowable, allocable, and reasonable per FAR cost principles.

  7. When a contractor receives a progress payment, the government obtains a security interest in the contractor's property under FAR 32.503. This is known as:

    Answer: The government's title to work in process

    FAR 32.503 provides that the government obtains title to all work in process and materials allocable to the contract upon making progress payments.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. ncmahq.org — Exam format, passing score, retake policy, score release, time limit, score validity, fees, test dates, test delivery · verified Oct 2026
Contract Financing & Payments Flashcards — CFCM Study Cards with Answers