A field builder discovers that underground utilities were not properly marked before excavation begins. What is the FIRST action to take?
Answer: Stop work immediately and call 811 to have utilities located
Work must stop immediately and 811 must be called to have utilities properly located before any excavation resumes.
Which document establishes the official legal boundaries of a construction site?
Answer: The boundary survey prepared by a licensed surveyor
A boundary survey conducted by a licensed land surveyor is the legally recognized document establishing property lines.
When managing a site in a flood zone, what is typically required before construction begins?
Answer: An elevation certificate and FEMA compliance review
FEMA-regulated flood zones require an elevation certificate and compliance with National Flood Insurance Program standards.
A site manager notices that a subcontractor's crew is working without proper fall protection at 8 feet above grade. Under OSHA standards, fall protection is required in construction at what minimum height?
Answer: 6 feet
OSHA 29 CFR 1926.502 requires fall protection in construction when workers are at or above 6 feet.
What is the purpose of a site logistics plan on a large construction project?
Answer: To coordinate material deliveries, staging areas, and traffic flow on site
A site logistics plan coordinates how materials are delivered, staged, and moved, and how site traffic flows to maximize efficiency and safety.
Which type of site meeting is typically held at the beginning of each workday to coordinate tasks and address safety?
Answer: Toolbox talk
A toolbox talk (also called a tailgate meeting) is a brief daily safety and coordination meeting held with field crews.
When a field builder encounters soil that is classified as Type C during trenching operations, what is the maximum allowable slope for an open trench per OSHA?
Answer: 1½:1 (horizontal:vertical)
OSHA requires Type C soil, the least stable classification, to be sloped at no steeper than 1½:1 (horizontal to vertical).