Which document formally authorizes a project and identifies the project manager's authority?
Answer: Project Charter
The project charter officially authorizes the project, names the project manager, and grants authority to apply organizational resources.
When sequencing construction activities, a 'Finish-to-Start' (FS) dependency means:
Answer: The successor cannot start until the predecessor finishes
Finish-to-Start is the most common dependency type, requiring the predecessor activity to be complete before the successor begins.
A field builder notes that the project's Schedule Performance Index (SPI) is 0.85. What does this mean?
Answer: The project is performing at 85% of the planned schedule rate
An SPI less than 1.0 means the project is behind schedule; 0.85 indicates only 85 cents of planned work is being accomplished per dollar of scheduled work.
Which type of schedule shows tasks as horizontal bars along a timeline and is most commonly used for communicating progress to field crews?
Answer: Gantt Chart
Gantt charts display tasks as horizontal bars against a calendar, making them easy for field crews to read and follow.
During project planning, a Work Breakdown Structure (WBS) is used primarily to:
Answer: Decompose project scope into manageable deliverables and work packages
The WBS breaks the total project scope into smaller, manageable components, providing the foundation for scheduling, costing, and assigning work.
A field builder must comply with a contract milestone requiring a building pad to be complete by a specific date. This is an example of:
Answer: An external constraint imposed on the schedule
Contractual milestone dates are external constraints that impose hard schedule boundaries regardless of internal sequencing logic.
What is the purpose of a project schedule 'baseline update' as opposed to a simple schedule update?
Answer: A baseline update formally re-approves the schedule after a significant approved change
Baseline updates require formal change control approval and reset the performance measurement reference point due to significant approved scope or schedule changes.