A Six Sigma project charter states the problem as 'cycle time is too long.' Why is this problem statement considered inadequate?
-
A
It does not name the responsible Black Belt
-
B
It lacks a quantified baseline, specific location, and measurable gap
-
C
It should describe the root cause instead
-
D
It must include customer complaints to be valid