A Black Belt uses the DMAIC roadmap for an existing process problem. When should a DFSS (DMADV) approach be used instead?
-
A
When the process has too many defects to count
-
B
When no existing process exists or the current process cannot meet requirements even with improvement
-
C
When the improvement timeline is too short for DMAIC
-
D
When the project sponsor prefers a design approach