A lean team calculates that takt time is 60 seconds but cycle time at a bottleneck station is 80 seconds. What is the correct lean response?
-
A
Add a second shift to meet demand
-
B
Reduce cycle time at the bottleneck station through waste elimination or additional resources
-
C
Increase takt time by reducing customer demand targets
-
D
Move inventory to a supermarket upstream of the bottleneck