A Black Belt discovers that a proposed project's problem statement reads: 'Improve customer satisfaction in the shipping department.' What is the PRIMARY deficiency in this problem statement?
-
A
It does not identify the root cause
-
B
It lacks quantifiable metrics and a specific baseline
-
C
It does not name the process owner
-
D
It fails to mention the Six Sigma methodology