In a Lean enterprise, 'takt time' is best defined as:
-
A
The average time a machine takes to complete one cycle
-
B
The rate at which products must be completed to meet customer demand
-
C
The total elapsed time from order placement to delivery
-
D
The maximum allowable defect rate per production shift