An energy auditor is performing a Level II audit and finds 15-minute interval electricity data shows demand spikes lasting only 1-2 intervals. What is the most cost-effective first step to address this?
-
A
Install a large battery energy storage system to shave all peaks
-
B
Investigate whether the spikes are caused by equipment with staggered start sequencing that could be adjusted
-
C
Upgrade the utility service to a higher demand tier to reduce penalty rates
-
D
Install a power factor correction capacitor bank at the main panel