Scrum Framework & Ceremonies Flashcards

7 cards from real CAE practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Scrum Framework & Ceremonies flashcards as text
  1. A Product Owner wants to cancel a Sprint. Under what condition is this allowed in Scrum?

    Answer: When the Sprint Goal becomes obsolete

    Only the Product Owner has the authority to cancel a Sprint, and only if the Sprint Goal has become obsolete.

  2. How does Scrum ensure that the Increment produced meets quality standards?

    Answer: Through the Definition of Done applied consistently to each Increment

    The Definition of Done establishes the quality criteria that every Increment must meet before it is considered complete.

  3. In a Sprint Review, who presents the Increment to stakeholders?

    Answer: The entire Scrum Team collaboratively

    The entire Scrum Team presents the Increment during the Sprint Review, though the Product Owner often leads the discussion.

  4. What is the time-box for Sprint Planning in a two-week Sprint?

    Answer: 4 hours

    Sprint Planning is time-boxed to a maximum of 8 hours for a one-month Sprint, so a two-week Sprint typically uses about 4 hours.

  5. A team member raises a technical impediment during the Daily Scrum that requires a long discussion. What is the best approach?

    Answer: Note it and schedule a separate meeting with the relevant people after the Daily Scrum

    Detailed problem-solving discussions should happen after the Daily Scrum with only those who need to be involved, keeping the event to 15 minutes.

  6. What outcome does the Sprint Retrospective produce according to Scrum?

    Answer: A plan for implementing improvements to the team's way of working

    The primary output of the Sprint Retrospective is an actionable plan for improvements the Scrum Team will implement in the next Sprint.

  7. Which statement accurately describes the relationship between Sprints?

    Answer: A new Sprint starts immediately after the conclusion of the previous Sprint

    In Scrum, a new Sprint starts immediately after the previous Sprint ends, ensuring a continuous development rhythm.