Scrum Framework & Ceremonies Flashcards

7 cards from real CAE practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Scrum Framework & Ceremonies flashcards as text
  1. During a Sprint Review, a stakeholder requests a major feature change that wasn't in the original Sprint Goal. What should the Scrum Team do?

    Answer: Note the feedback and add it to the Product Backlog for future consideration

    Sprint Reviews generate feedback that is captured in the Product Backlog; changes are not added mid-Sprint.

  2. How long is the time-box for the Daily Scrum?

    Answer: 15 minutes

    The Daily Scrum is a 15-minute time-boxed event for the Developers to inspect progress and adapt their plan.

  3. Who is responsible for facilitating the Sprint Retrospective?

    Answer: The Scrum Master

    The Scrum Master facilitates the Sprint Retrospective, ensuring it is productive and positive.

  4. A team consistently finishes Sprint Planning with unclear Sprint Goals. What is the most likely root cause?

    Answer: The Product Backlog is not sufficiently refined before Sprint Planning

    Unclear Sprint Goals often result from a Product Backlog that lacks refinement, making it hard to form a coherent objective.

  5. Which statement best describes the purpose of the Sprint Retrospective?

    Answer: To inspect how the last Sprint went and identify improvements

    The Sprint Retrospective focuses on improving team processes, interactions, and tools based on the previous Sprint.

  6. In Scrum, what happens if the Development Team realizes mid-Sprint they cannot complete all Sprint Backlog items?

    Answer: They remove items from the Sprint Backlog and negotiate scope with the Product Owner

    Developers can negotiate scope with the Product Owner when Sprint Backlog content needs adjustment, but the Sprint duration stays fixed.

  7. What is the maximum recommended Sprint length in Scrum?

    Answer: 1 month

    Scrum Guide specifies Sprints are one month or less; one month is the maximum to limit risk and enable frequent inspection.