Which scheduling technique is most appropriate during early project phases when full design details are not yet available but a milestone-level timeline is required?
-
A
Detailed CPM network
-
B
Rolling wave planning with milestone schedule
-
C
Resource-leveled baseline
-
D
S-curve analysis