CEP Project Management & Scheduling 5 — Questions and Answers
Question 1: Which scheduling technique is most appropriate during early project phases when full design details are not yet available but a milestone-level timeline is required?
- Detailed CPM network
- Rolling wave planning with milestone schedule (Correct answer)
- Resource-leveled baseline
- S-curve analysis
Correct answer: Rolling wave planning with milestone schedule
Rolling wave planning allows early phases to be planned in detail while future phases are represented at a summary or milestone level, progressively elaborated as information becomes available.
Question 2: A Schedule Variance (SV) of −$50,000 on a construction project means:
- The project has spent $50,000 more than budgeted
- The project is $50,000 worth of work behind the planned schedule (Correct answer)
- The project needs $50,000 more funding
- The project's contingency is $50,000 short
Correct answer: The project is $50,000 worth of work behind the planned schedule
Schedule Variance (SV = EV − PV) of −$50,000 means $50,000 less work has been earned than was planned, indicating schedule slippage measured in cost terms.
Question 3: In project scheduling, the 'hammock activity' is best described as:
- An activity with no predecessors
- A summary activity that spans between two specific points in the schedule and derives its duration from those points (Correct answer)
- An activity on the critical path with zero float
- A milestone with no duration
Correct answer: A summary activity that spans between two specific points in the schedule and derives its duration from those points
A hammock activity is a summary task whose duration is determined by the start of its first dependent activity and the finish of its last dependent activity.
Question 4: When reviewing a contractor's schedule for a large construction project, an owner's estimator should verify that the schedule includes adequate time for which activity that is often underestimated?
- Equipment delivery and owner-furnished material procurement lead times (Correct answer)
- Architect design reviews
- Final punch list only
- Post-completion warranty periods
Correct answer: Equipment delivery and owner-furnished material procurement lead times
Long-lead procurement for equipment and owner-furnished materials is frequently underestimated and can delay construction if not incorporated with accurate lead times in the schedule.
Question 5: Which document formally authorizes the project and provides the project manager with authority to apply organizational resources to project activities?
- Project Management Plan
- Project Charter (Correct answer)
- Scope Statement
- Work Authorization System
Correct answer: Project Charter
The Project Charter formally authorizes the project's existence and grants the project manager the authority needed to commit resources to project work.
Question 6: In a construction project estimate, 'schedule-related costs' such as general conditions and overhead are directly tied to project duration because:
- They are fixed regardless of project length
- They accrue on a time-based rate and increase proportionally as the project duration extends (Correct answer)
- They are only incurred during the construction phase
- They are calculated as a percentage of material costs
Correct answer: They accrue on a time-based rate and increase proportionally as the project duration extends
General conditions costs (supervision, temporary facilities, site utilities) accrue daily and directly increase with project duration, making schedule compression a key cost reduction strategy.
Question 7: A project team is developing a schedule for a design-build contract. Which scheduling approach best accommodates the overlapping of design and construction activities?
- Pure sequential phasing with no overlaps
- Phased fast-track scheduling with design packages released to construction as they are completed (Correct answer)
- Activity-on-Arrow network with mandatory Finish-to-Start logic only
- Milestone-only schedule with no activity detail
Correct answer: Phased fast-track scheduling with design packages released to construction as they are completed
Phased fast-tracking on design-build projects releases completed design packages to construction in sequence, allowing work to overlap and compress the overall delivery schedule.
Which scheduling technique is most appropriate during early project phases when full design details are not yet available but a milestone-level timeline is required?