  1. Under RCRA, a facility generating 1,000 kg or more of non-acute hazardous waste in a calendar month is classified as which generator category?

    Answer: Large Quantity Generator

    Generating 1,000 kg or more of non-acute hazardous waste per month makes a site a Large Quantity Generator under 40 CFR 262.

  2. How long may a Large Quantity Generator accumulate hazardous waste on-site without a storage permit?

    Answer: 90 days

    LQGs may accumulate hazardous waste for up to 90 days without a RCRA storage permit.

  3. A Small Quantity Generator located more than 200 miles from the nearest TSDF may accumulate waste for up to how many days?

    Answer: 270 days

    SQGs normally get 180 days, extended to 270 days if waste must travel over 200 miles to a TSDF.

  4. Which of the following is NOT one of the four RCRA hazardous waste characteristics?

    Answer: Persistence

    The four characteristics are ignitability, corrosivity, reactivity, and toxicity; persistence is not one of them.

  5. An aqueous waste is characteristically corrosive (D002) under RCRA if its pH is:

    Answer: Less than or equal to 2 or greater than or equal to 12.5

    Aqueous wastes with pH at or below 2 or at or above 12.5 exhibit the corrosivity characteristic.

  6. A liquid waste is considered ignitable (D001) if its flash point is below:

    Answer: 140°F (60°C)

    Liquids with a flash point below 60°C (140°F) exhibit the ignitability characteristic.

  7. Which 1984 amendment to RCRA established the Land Disposal Restrictions program?

    Answer: Hazardous and Solid Waste Amendments

    HSWA of 1984 created the Land Disposal Restrictions requiring treatment before land disposal.

Written and edited by , founder of Practice Test Geeks, with AI assistance. Exam facts are checked against the official sources linked below. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. ndep.nv.gov — Eligibility, score release, test delivery, exam format, passing score, retake policy, test dates, time limit, fees · verified Nov 2026
  2. leg.state.nv.us — Score validity · verified Nov 2026