A manufacturing facility has a consistent electrical load of 500 kW.
The plant's power factor is measured at 0.75 lagging.

To avoid utility penalties and reduce demand charges, the facility manager wants to improve the power factor to 0.95 lagging.

Which of the following is the closest to the required size of a capacitor bank (in kVAR) to achieve this correction?

Select your answer