A vendor quotes a material price with a 90-day validity period. The project schedule shows delivery needed in 120 days. The estimator should:
-
A
Use the quoted price and hope it holds
-
B
Request a price extension or add an escalation contingency
-
C
Ignore the quote and use historical pricing
-
D
Reduce the quoted price by 10% as a buffer