(CEC) Construction Estimator Certification Practice Test
CEC CEC Value Engineering & Cost Control
What is the primary goal of value engineering (VE) in construction estimating?
Select your answer
A
Increase project complexity
B
Achieve required function at the lowest overall cost
C
Maximize material quantities
D
Extend project schedules
Hint