CDT Contract Documents & Specifications 1 — Questions and Answers
Question 1: Which CSI MasterFormat division covers Concrete in construction specifications?
- Division 02
- Division 03 (Correct answer)
- Division 04
- Division 05
Correct answer: Division 03
CSI MasterFormat Division 03 covers Concrete, including cast-in-place, precast, and specialty concrete work.
Question 2: What is the primary purpose of a Project Manual in construction?
- To show graphical design intent
- To compile specifications, bidding requirements, and contract forms (Correct answer)
- To list the project schedule
- To document shop drawing approvals
Correct answer: To compile specifications, bidding requirements, and contract forms
The Project Manual compiles written documents including specifications, bidding requirements, and contract forms that supplement the drawings.
Question 3: In CSI SectionFormat, which part of a specification section contains execution procedures?
- Part 1 – General
- Part 2 – Products
- Part 3 – Execution (Correct answer)
- Part 4 – Closeout
Correct answer: Part 3 – Execution
Part 3 – Execution describes how products are installed, applied, or constructed in the field.
Question 4: Which specification type lists acceptable manufacturers by name and requires no substitution?
- Descriptive specification
- Performance specification
- Proprietary specification (Correct answer)
- Reference standard specification
Correct answer: Proprietary specification
A proprietary specification names a specific product or manufacturer, leaving no room for substitution unless explicitly allowed.
Question 5: What document formally authorizes changes to the contract sum or contract time during construction?
- Request for Information
- Construction Change Directive
- Change Order (Correct answer)
- Supplemental Instruction
Correct answer: Change Order
A Change Order is the executed agreement between owner, contractor, and architect that formally modifies the contract sum or time.
Question 6: Which AIA document is commonly used as the General Conditions for a stipulated sum contract?
- AIA A101
- AIA A201 (Correct answer)
- AIA B101
- AIA G701
Correct answer: AIA A201
AIA A201, General Conditions of the Contract for Construction, governs the rights and responsibilities of all parties in most U.S. projects.
Which CSI MasterFormat division covers Concrete in construction specifications?