← All CDT Flashcard Decks

Construction Administration Flashcards

6 cards from real CDT practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 6 Construction Administration flashcards as text
  1. What is the architect's primary responsibility during construction administration?

    Answer: Observing construction for general conformance with the contract documents

    During construction administration, the architect observes the work to determine general conformance with the contract documents — not to supervise or direct the contractor.

  2. What is the purpose of a submittal log during construction administration?

    Answer: To record and track all shop drawings, product data, and samples submitted for architect review

    A submittal log tracks the status of all required shop drawings, product data, and samples to ensure timely review and approval before materials are fabricated or installed.

  3. When an architect reviews a shop drawing and stamps it 'Revise and Resubmit,' what must the contractor do?

    Answer: Revise the shop drawing per the comments and resubmit for another review

    'Revise and Resubmit' means the shop drawing has deficiencies that must be corrected and re-reviewed before fabrication or installation may proceed.

  4. Who is responsible for maintaining a daily construction log on a project?

    Answer: The contractor, documenting daily work activities, workforce, weather, and events

    The contractor maintains a daily construction log documenting workforce counts, weather conditions, work performed, and any notable events or delays.

  5. What is a punch list in the context of construction administration?

    Answer: A list of incomplete or deficient items that must be corrected before final completion

    A punch list documents remaining deficiencies and incomplete items identified at substantial completion that the contractor must correct before final payment.

  6. Under AIA A201, what happens if the contractor believes extra compensation is warranted but has not provided timely written notice?

    Answer: The contractor may waive the right to a claim by failing to provide required timely written notice

    AIA A201 requires timely written notice of claims; failure to provide notice within the specified period can waive the contractor's right to additional compensation.