← All CDS Flashcard Decks

Project Planning & Scheduling Flashcards

7 cards from real CDS practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Project Planning & Scheduling flashcards as text
  1. Which phase of demolition project planning involves reviewing as-built drawings, structural reports, and utility records?

    Answer: Pre-construction/due diligence phase

    The pre-construction or due diligence phase involves reviewing all available records to understand the structure's composition and potential hazards before planning begins.

  2. What does 'critical path' mean in the context of a demolition project schedule?

    Answer: The longest sequence of dependent tasks that determines the minimum project duration

    The critical path is the longest chain of dependent tasks; any delay to a critical path activity directly delays project completion.

  3. During project planning, why should a demolition supervisor coordinate with local traffic authorities?

    Answer: To plan truck haul routes, control debris transport timing, and prevent road damage or public traffic hazards

    Coordinating haul routes and transport timing with traffic authorities prevents road damage, minimizes public disruption, and keeps debris trucks in compliance with local regulations.

  4. A demolition project plan should include a communication plan that specifies:

    Answer: Who receives notifications, how often, and what information is shared among the owner, supervisor, subcontractors, and regulators

    A communication plan defines notification protocols, reporting frequency, and information flow among all project stakeholders and regulatory parties.

  5. When planning equipment requirements for a demolition project, which factor should MOST influence the choice of primary demolition equipment?

    Answer: Structural type, material composition, site access constraints, and debris removal method

    Equipment selection must match the structural type, materials, site access, and debris handling plan to ensure safe and efficient demolition.

  6. A project schedule shows that hazardous material abatement and structural shoring are on the critical path. What does this mean for the CDS supervisor?

    Answer: Delays in abatement or shoring will directly delay the entire project completion date

    Critical path tasks directly control project completion, so any delay in abatement or shoring extends the overall project timeline.

  7. What is the role of a work breakdown structure (WBS) in demolition project planning?

    Answer: It decomposes the project scope into manageable work packages that can be scheduled, costed, and assigned

    A WBS breaks the total project scope into smaller, manageable work packages enabling accurate scheduling, cost estimating, and responsibility assignment.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. demolitionassociation.com — Test delivery, test dates, score validity, fees, exam format, passing score, retake fee, retake policy, score release · verified Oct 2026