Project Planning & Scheduling Flashcards

7 cards from real CDS practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Project Planning & Scheduling flashcards as text
  1. During the planning phase of a demolition project, what is the PRIMARY purpose of a pre-demolition survey?

    Answer: To identify hazardous materials, structural elements, and site conditions

    A pre-demolition survey identifies hazardous materials, structural vulnerabilities, and site conditions that affect safety planning and sequencing.

  2. Which scheduling method shows task dependencies using arrows and nodes to represent activities and their relationships?

    Answer: PERT/CPM network diagram

    PERT/CPM network diagrams use arrows and nodes to represent activities and their logical dependencies, identifying the critical path.

  3. A demolition contractor discovers underground fuel storage tanks not shown on original blueprints. What is the CORRECT next step?

    Answer: Stop work, notify the owner and regulatory agencies, and update the project plan

    Undiscovered underground storage tanks require immediate work stoppage, notification of the owner and regulators, and project plan revision.

  4. In demolition project scheduling, 'float' or 'slack' refers to:

    Answer: The amount of time a task can be delayed without affecting the project completion date

    Float (or slack) is the amount of time a non-critical activity can be delayed without delaying the overall project completion date.

  5. When planning the sequence of demolition for a multi-story building, which general principle should guide the work order?

    Answer: Work from the top down to maintain structural stability

    Demolition generally proceeds top-down so lower structural members continue to support remaining upper floors until they are removed.

  6. Which document specifies the types and amounts of salvageable materials to be recovered before full demolition begins?

    Answer: Selective demolition or deconstruction plan

    A selective demolition or deconstruction plan identifies salvageable materials, their locations, and the sequence for careful removal prior to full demolition.

  7. A CDS supervisor is developing a waste management plan. Which factor is MOST critical when planning debris hauling schedules?

    Answer: Volume of material generated per day matched to truck capacity and disposal site hours

    Matching daily debris volume to truck capacity and disposal site operating hours prevents bottlenecks and ensures continuous, compliant waste removal.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. demolitionassociation.com — Test delivery, test dates, score validity, fees, exam format, passing score, retake fee, retake policy, score release · verified Oct 2026