  1. Under EPA's NESHAP for asbestos, the threshold quantity of friable asbestos-containing material that triggers full regulatory compliance during demolition is:

    Answer: 260 linear feet or 160 square feet

    EPA NESHAP 40 CFR 61.145 specifies that facilities with 260+ linear feet of pipe insulation or 160+ square feet of other RACM trigger full asbestos demolition regulations.

  2. When a historic structure is being partially demolished, which code requires consultation with the State Historic Preservation Officer (SHPO) before work begins?

    Answer: 36 CFR Part 800 (Section 106 Process)

    36 CFR Part 800 implements Section 106 of the National Historic Preservation Act, requiring federal undertaking review and SHPO consultation before demolition of historic properties.

  3. OSHA 29 CFR 1926.860 requires that floor openings created during demolition be guarded with covers capable of supporting a minimum load of:

    Answer: Two times the maximum intended load

    OSHA 1926.860 requires floor opening covers to support at least twice the weight of the equipment, material, or employees likely to cross them.

  4. Under RCRA (Resource Conservation and Recovery Act), demolition debris from a commercial structure is classified as which waste type by default?

    Answer: Solid waste subject to state landfill regulations

    RCRA classifies standard demolition debris as solid waste, which is regulated at the state level and subject to applicable landfill acceptance requirements.

  5. Which OSHA standard requires that a competent person inspect all shoring systems supporting adjacent structures during demolition at minimum:

    Answer: Daily before work begins

    OSHA requires a competent person to inspect shoring and bracing systems daily before work begins to identify any deterioration or movement overnight.

  6. The term 'progressive collapse' in IBC Chapter 16 refers to which specific structural failure scenario relevant to demolition sequencing?

    Answer: Disproportionate spread of local failure through a structure

    IBC Chapter 16 defines progressive collapse as a situation where local failure of a primary structural element causes disproportionate widespread collapse through the structure.

  7. According to OSHA 29 CFR 1926.852, chutes used to remove debris from heights greater than 20 feet must be enclosed and discharge into which type of container?

    Answer: An enclosed container with a tight-fitting lid or screen

    OSHA 1926.852 requires that high-rise debris chutes discharge into an enclosed container to control dust and prevent debris from scattering at the collection point.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. demolitionassociation.com — Test delivery, test dates, score validity, fees, exam format, passing score, retake fee, retake policy, score release · verified Oct 2026