What is the key difference between RPO and RTO in a data centre disaster recovery plan?
-
A
RPO measures recovery speed; RTO measures data loss tolerance
-
B
RPO is the maximum acceptable data loss; RTO is the maximum acceptable downtime duration
-
C
RPO applies to hardware; RTO applies to software recovery
-
D
RPO is set by regulators; RTO is set by the business