A data center technician is performing a generator load bank test. What is the primary purpose of this test?
-
A
Verify fuel consumption rates under normal load
-
B
Confirm the generator can sustain rated load and temperature under simulated conditions
-
C
Test the automatic transfer switch response time only
-
D
Measure generator noise levels at full load