During a preventive maintenance window, a UPS battery string fails a capacity test at 78% of rated capacity. What is the recommended action?
-
A
Continue monitoring and retest in 30 days
-
B
Replace the entire battery string immediately
-
C
Replace only the failed cells and retest
-
D
Reduce the load on that UPS by 22%