Capacity Planning and Power Budgeting Flashcards
7 cards from real CDCP practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Capacity Planning and Power Budgeting flashcards as text
What is the approximate apparent power capacity of a 400 V, 32 A, three-phase rack PDU (before derating)?
Answer: 22.2 kVA
400 V x 32 A x 1.732 is about 22.2 kVA.
Modern servers with active power factor correction typically present a power factor of about:
Answer: 0.95-0.99
Active PFC power supplies usually achieve 0.95 or higher at moderate to high load.
What is a key capacity-planning benefit of a modular, phased infrastructure build-out?
Answer: It lowers upfront capital and keeps equipment loaded nearer its efficient range
Adding capacity in steps as demand grows avoids stranded capital and the poor efficiency of lightly loaded infrastructure.
Each UPS in a 2N system runs at only 20% load. What is the main efficiency concern?
Answer: UPS efficiency is lower at light load, so losses are proportionally higher
Double-conversion UPS efficiency typically falls at low load, which raises losses and PUE.
When should expansion planning be triggered for a growing data center?
Answer: When the remaining headroom will run out within the procurement and construction lead time
The trigger point must allow for design, procurement and build lead times, so new capacity arrives before the existing headroom is used up.
A three-phase PDU shows L1 at 90%, L2 at 40% and L3 at 35% of rating. What is the main capacity risk?
Answer: L1 may trip while overall capacity remains unused, and neutral current increases
Phase imbalance strands capacity on the lightly loaded phases and risks overloading the heavily loaded one.
A design calls for 800 kW of IT load at a PUE of 1.4, with a site power factor of 0.9. About how large a utility supply in kVA is needed?
Answer: 1,244 kVA
Total load is 800 x 1.4 = 1,120 kW, and 1,120 / 0.9 is about 1,244 kVA.
Written and edited by Nathan Beja, founder of Practice Test Geeks, with AI assistance. Exam facts are checked against the official sources linked below. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- epi-ap.com — Eligibility, exam format, passing score, score validity, retake policy, renewal, test delivery, exam information · verified Oct 2026
- exin.com — Time limit · verified Oct 2026