CD Risk Management & Mitigation 3 — Questions and Answers
Question 1: A client verbally requests a design change during a phone call. What is the drafter's best risk mitigation step before revising the drawings?
- Obtain written confirmation of the change and route it through the formal change-order process (Correct answer)
- Make the change immediately since the client is the ultimate authority
- Wait until the client calls again to confirm they were serious
- Make the change but keep the old drawing hidden in case of problems
Correct answer: Obtain written confirmation of the change and route it through the formal change-order process
Written change confirmation through a formal process prevents scope disputes and unauthorized revisions.
Question 2: Which backup strategy best protects a drafting office against data loss from ransomware or server failure?
- The 3-2-1 approach: three copies of data on two different media types with one copy stored offsite (Correct answer)
- Saving all files twice on the same network server
- Emailing important drawings to a personal account weekly
- Relying on each drafter's local hard drive as the backup
Correct answer: The 3-2-1 approach: three copies of data on two different media types with one copy stored offsite
The 3-2-1 rule ensures at least one uninfected, physically separate copy survives most disaster scenarios.
Question 3: A drafter notices that a vendor-supplied shop drawing conflicts with the design intent drawings. Approving it without comment creates which type of risk?
- Professional liability risk, since the reviewer may share responsibility for the resulting error (Correct answer)
- No risk, because vendors are always responsible for their own drawings
- Only schedule risk, since conflicts never affect safety
- Financial risk to the vendor only
Correct answer: Professional liability risk, since the reviewer may share responsibility for the resulting error
Reviewing and approving a conflicting shop drawing can make the reviewing firm partly liable for the error.
Question 4: In a project risk register, what does a 'risk trigger' identify?
- An early warning event or condition indicating the risk is about to occur (Correct answer)
- The person assigned to own the risk
- The total budget reserved for all project risks
- The software used to draw the risk matrix
Correct answer: An early warning event or condition indicating the risk is about to occur
A trigger is the observable warning sign that tells the team a risk event is materializing.
Question 5: Why do drafting standards require revision clouds and revision blocks on updated drawings?
- They make changes traceable so field crews can identify exactly what was modified, reducing construction-from-stale-information errors (Correct answer)
- They are decorative elements required only for plotting
- They allow drafters to avoid updating the title block
- They increase the drawing sheet count for billing purposes
Correct answer: They make changes traceable so field crews can identify exactly what was modified, reducing construction-from-stale-information errors
Clearly flagged revisions prevent builders from missing changes and constructing from superseded information.
Question 6: A drafting team accepts a fast-track project where design proceeds while construction begins. Which mitigation best addresses the elevated rework risk?
- Freezing and formally releasing design packages in stages, with strict interface coordination between packages (Correct answer)
- Skipping quality checks to keep pace with construction
- Issuing all drawings as preliminary so no one can rely on them
- Refusing to communicate with the construction team until design is complete
Correct answer: Freezing and formally releasing design packages in stages, with strict interface coordination between packages
Staged design freezes with managed interfaces control rework exposure inherent in fast-track delivery.
Question 7: Which situation represents residual risk after mitigation controls are applied?
- The small chance of an error remaining even after independent checking and CAD standards are enforced (Correct answer)
- The original risk level before any controls existed
- A risk that was transferred entirely to an insurer
- A risk listed in the register that was later proven impossible
Correct answer: The small chance of an error remaining even after independent checking and CAD standards are enforced
Residual risk is the exposure that remains after all planned controls are in place.
A client verbally requests a design change during a phone call.
What is the drafter's best risk mitigation step before revising the drawings?