A construction specification requires a '24-hour notice' for inspections. This refers to:
-
A
The time the inspector must wait before rejecting work
-
B
Advance notification the contractor must give before requesting an inspection
-
C
The window within which the owner must respond to RFIs
-
D
The delay period after concrete placement before stripping forms