Which scheduling technique is best suited for projects with high uncertainty in activity durations, as it uses three-point estimates (optimistic, most likely, pessimistic)?
-
A
Critical Path Method (CPM)
-
B
Gantt chart method
-
C
Program Evaluation and Review Technique (PERT)
-
D
Linear scheduling method