In a Construction Manager at-Risk (CMaR) delivery method, when does the construction manager typically provide a Guaranteed Maximum Price (GMP)?
-
A
At project inception before design begins
-
B
After design development or construction documents are sufficiently complete
-
C
Only after all subcontractor bids are received and construction starts
-
D
At the time the owner selects the construction manager