โ† All CCS Flashcard Decks

Quality Control & Inspection Flashcards

7 cards from real CCS practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Quality Control & Inspection flashcards as text
  1. In construction quality management, what is a 'quality audit'?

    Answer: A systematic, independent examination to determine if quality activities comply with planned arrangements

    A quality audit is a formal, documented, and independent review verifying that quality activities and results conform to planned arrangements.

  2. Which action by the architect is MOST appropriate when shop drawings reveal a contractor-proposed deviation from the contract documents?

    Answer: Return the shop drawing with a notation that the deviation requires a formal change order or substitution request

    Deviations from contract documents must be processed through a formal change order or substitution request, not silently approved via shop drawing stamp.

  3. Which sampling method for soil compaction testing involves collecting a sample from the actual compacted fill and testing its dry density in the field?

    Answer: Nuclear density gauge test

    A nuclear density gauge measures in-place dry density and moisture content of compacted fill directly in the field, enabling immediate QC feedback.

  4. A CCS is specifying inspection requirements for high-strength structural bolts. Which standard governs the installation and inspection of these bolts?

    Answer: RCSC Specification for Structural Joints

    The Research Council on Structural Connections (RCSC) Specification governs the design, installation, and inspection of high-strength bolted structural joints.

  5. What is the significance of a 'punchlist' (or deficiency list) in construction quality control?

    Answer: It documents incomplete or nonconforming work that must be corrected before final acceptance

    A punchlist catalogs remaining deficiencies that the contractor must correct to achieve substantial or final completion.

  6. Which condition would MOST likely justify increasing the frequency of Special Inspections during construction?

    Answer: A pattern of repeated nonconformances is found in the same work type

    Recurring deficiencies in the same work type indicate a systemic quality problem warranting more frequent oversight until the issue is resolved.

  7. A specifier writes a quality control section requiring the contractor to maintain a 'quality log.' What information should this log PRIMARILY capture?

    Answer: Records of inspections, tests, nonconformances, and corrective actions taken

    A quality log is the primary QC record documenting inspection results, test outcomes, nonconformances, and the corrective actions that resolved them.