Project Planning & Scheduling Flashcards

7 cards from real CCS practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Project Planning & Scheduling flashcards as text
  1. Which scheduling method uses arrow diagrams where activities are represented on arrows and nodes represent events?

    Answer: Arrow Diagramming Method (ADM)

    Arrow Diagramming Method (ADM), also called Activity-on-Arrow (AOA), represents activities on arrows with nodes as events.

  2. In construction scheduling, what does 'float' or 'slack' represent?

    Answer: The amount of time an activity can be delayed without delaying the project completion

    Float (or slack) is the amount of time an activity can be delayed without affecting the overall project completion date.

  3. A construction specifier is reviewing a project schedule and notices the critical path has changed after a subcontractor delay. What is the term for this new critical path?

    Answer: Near-critical path

    A near-critical path has very little float and can become the critical path if further delays occur on those activities.

  4. Which document establishes the agreed-upon project schedule baseline against which actual progress is measured?

    Answer: Approved baseline schedule

    The approved baseline schedule is the formally agreed-upon schedule that serves as the benchmark for measuring project performance.

  5. What is the primary purpose of a construction project's 'look-ahead schedule'?

    Answer: To provide a short-term detailed plan for upcoming work over the next 2-6 weeks

    A look-ahead schedule provides a detailed short-term view (typically 2-6 weeks) to coordinate immediate upcoming work and resources.

  6. Under AIA contract documents, which party typically has the contractual obligation to prepare and submit the construction schedule?

    Answer: The contractor

    Under standard AIA contract documents, the contractor is responsible for preparing and submitting the construction schedule for the architect's review.

  7. When a specification requires the contractor to submit a 'schedule of values,' what is its primary purpose?

    Answer: To allocate the contract sum among portions of work for progress payment applications

    A schedule of values allocates the contract sum across work items so that progress payment applications can be accurately evaluated.