Construction Documentation & Specifications Flashcards

7 cards from real CCS practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Construction Documentation & Specifications flashcards as text
  1. Which contract document takes precedence when a conflict exists between the drawings and the specifications?

    Answer: The Agreement typically states which governs, or both are treated as complementary

    Most standard agreements (e.g., AIA A201) treat drawings and specifications as complementary; conflicts are resolved by the architect, and the Agreement specifies priority if needed.

  2. A 'closed' proprietary specification names:

    Answer: A single manufacturer with no substitutions allowed

    A closed proprietary specification names one specific manufacturer/product and explicitly states no substitutions are permitted.

  3. The Division 01 section 'Allowances' is used to:

    Answer: Include a fixed dollar amount in the bid for items whose final selection is not yet determined

    Allowances are specific dollar amounts included in the contract sum for items (often finish selections) whose final choice will be made later by the owner.

  4. What is the primary purpose of the 'Submittals' article in Part 1 of a specification section?

    Answer: To identify which submittals (shop drawings, product data, samples) the contractor must submit for that section

    The Submittals article in Part 1 identifies the specific submittal types required for that section's work so the contractor and architect know what must be reviewed.

  5. An RFI (Request for Information) during construction is used to:

    Answer: Seek clarification on ambiguous or incomplete contract document information

    An RFI is submitted by the contractor to the architect to obtain clarification or additional information about the contract documents without necessarily changing the scope or price.

  6. Which part of a three-part specification section would include requirements for mock-ups?

    Answer: Part 1 General — under Quality Assurance

    Mock-up requirements are a quality assurance tool and belong in the Quality Assurance article of Part 1 General, establishing standards before work proceeds.

  7. The term 'furnish' in specification language means to:

    Answer: Supply and deliver an item to the project site, ready for installation

    Per CSI defined terminology, 'furnish' means to supply, deliver, and where applicable unload — but not to install.