Time Management Flashcards
6 cards from real CCM practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 6 Time Management flashcards as text
What is the primary purpose of a project schedule in construction management?
Answer: To guide timely task execution
A project schedule is a critical tool that outlines all project activities, their durations, dependencies, and logical sequence. Its primary purpose is to provide a roadmap for timely task execution, ensuring that work is performed in the correct order and within planned timeframes. This helps manage resources, coordinate efforts, and meet project deadlines efficiently.
Which scheduling method is most commonly used in construction projects?
Answer: Critical Path Method
The Critical Path Method (CPM) is a widely used scheduling technique in construction management. It identifies the longest sequence of dependent activities (the critical path) that determines the shortest possible project duration. CPM helps project managers focus on critical tasks, manage float, and prevent delays to the overall project timeline.
What is a milestone in a project schedule?
Answer: A significant project event
A milestone in a project schedule represents a significant point or event in the project lifecycle, such as the completion of a major phase, a key deliverable, or a decision point. Milestones have zero duration and are used to track progress, mark achievements, and provide clear checkpoints for stakeholders.
What does float (or slack) represent in a project schedule?
Answer: The buffer time before delay impacts
Float, also known as slack, in a project schedule refers to the amount of time an activity can be delayed without delaying the project's overall completion date or the start of subsequent activities. It represents flexibility in the schedule, allowing managers to allocate resources and manage unforeseen issues without impacting critical deadlines.
Which tool is often used to visually track project timelines and activities?
Answer: Gantt chart
A Gantt chart is a popular bar chart used for project scheduling, which visually represents project activities against time. Each bar on the chart corresponds to a task, with its length indicating duration and its position showing start and end dates. Gantt charts are excellent for tracking progress, identifying dependencies, and communicating project timelines to stakeholders.
Which action should a construction manager take if a critical task is behind schedule?
Answer: Fast-track project activities
If a critical task is behind schedule, fast-tracking is a common technique to compress the schedule. This involves performing activities in parallel that would normally be done in sequence, or overlapping phases. While it can increase risk and potentially cost, fast-tracking aims to accelerate project completion and bring the project back on schedule.