  1. A construction company's 'over/under billing schedule' is used primarily to:

    Answer: Reconcile contract billing status with earned revenue across all projects

    The over/under billing schedule (WIP schedule) compares billed amounts to earned revenue on each project, identifying overbilled and underbilled positions.

  2. Under GAAP, heavy construction equipment is classified on the balance sheet as:

    Answer: Property, plant and equipment

    Heavy equipment used in operations is reported as property, plant and equipment (PP&E) on the balance sheet.

  3. In the context of a large-scale construction project budget, what is the primary difference between a contingency reserve and a management reserve?

    Answer: Contingency covers 'known unknowns,' while management reserve covers 'unknown unknowns'.

    The key distinction is based on the nature of the risk. A contingency reserve is allocated for identified risks, or 'known unknowns'—risks you know might happen but are not certain about the impact. A management reserve is for unforeseen risks, or 'unknown unknowns'—events that were not identified during planning. The project manager typically controls the contingency reserve, whereas the management reserve requires senior management approval to use.

  4. The assumption that states that business can divide up their activities into artificial time periods.

    Answer: Periodicity assumption

    The periodicity assumption states that businesses can divide up their activities into artificial time periods. This assumption allows businesses to prepare financial statements at regular intervals, such as monthly, quarterly or annually to provide useful information to users. It helps in measuring and reporting the financial performance and position of the business over a specific period, facilitating comparisons and analysis.

  5. A construction company qualifies as a small contractor and uses the completed-contract method (CCM) for recognizing income on its long-term contracts for regular tax purposes. For the purpose of calculating the Alternative Minimum Tax (AMT), what adjustment is generally required for these contracts?

    Answer: The contractor must use the Percentage-of-Completion Method (PCM) for all long-term contracts.

    For Alternative Minimum Tax (AMT) purposes, income from long-term contracts must generally be calculated using the Percentage-of-Completion Method (PCM), as defined in IRC Section 460(b). This means a company using the completed-contract method for regular tax must make an AMT adjustment for the difference between the income that would have been recognized under PCM and the zero income recognized under CCM in the years prior to completion. This is a common AMT preference item for construction contractors.

  6. Control over ______________ are necessary to provide for adequate documentation, clerical verification, overall review of estimated costs and approval of all bids by the appropriate levels of management.

    Answer: Project Administration and Contract Valuation

    Project Administration and Contract Valuation is the control area that encompasses documentation, clerical verification, review of estimated costs, and approval of bids, because these activities govern how contracts are valued and administered at the management level. Estimating and Bidding focuses on the preparation phase, while Jobsite Accounting and Billing Procedures handle execution-level financial tasks.

  7. A construction financial manager is analyzing project performance. The project has an earned value of $500,000 and an actual cost of $550,000. What is the Cost Performance Index (CPI), and what does it indicate?

    Answer: CPI is 0.91, indicating the project is over budget.

    The Cost Performance Index (CPI) is calculated by dividing the Earned Value (EV) by the Actual Cost (AC). In this scenario, CPI = $500,000 / $550,000 = 0.91. A CPI value less than 1 indicates that the project is over budget, meaning it is costing more to perform the work than was planned.

  8. In the audits of the financial statements of construction contractors, the areas that normally receive particular attention include all of the following except one:

    Answer: Construction Equipment's

    In construction audits, auditors focus on internal controls, operating systems and procedures, and project management because these directly affect how financial data is generated and reported. Construction equipment is a physical asset category, not a distinct area of audit procedure focus — equipment-related transactions are captured within other areas like contract costs rather than examined separately.

  9. How do joint checks issued by an owner directly to a subcontractor and general contractor together primarily benefit construction cash flow management?

    Answer: They ensure subcontractors are paid from owner funds, reducing the GC's cash outlay and lien exposure

    Joint checks require both parties to endorse them, ensuring sub-tier payments come directly from the owner's funds rather than the GC's operating cash, reducing the GC's financing burden and lien risk.

  10. In construction finance, 'overbilling' creates a balance sheet liability known as:

    Answer: Contract liabilities (billings in excess)

    When a contractor bills more than the percentage of completion warrants, the excess is a contract liability (billings in excess of costs and estimated earnings).

  11. Which of these is not included as a separate item in the basic accounting equation?

    Answer: Revenue

    Revenue is not included as a separate item in the basic accounting equation. The basic accounting equation states that Assets = Liabilities + Stockholder's equity. Revenue is not a separate item in this equation because it is considered a component of stockholder's equity. Revenue represents the inflow of assets (such as cash or accounts receivable) resulting from the sale of goods or services and increases stockholder's equity. Therefore, revenue is not listed as a separate item in the equation.

  12. A bonded contractor is formally declared in default by the project owner (the obligee). Under the terms of a standard performance bond, which of the following is NOT a typical option for the surety to remedy the default?

    Answer: Pay the penal sum of the bond in cash to the obligee, allowing the obligee to manage project completion independently.

    While the surety's liability is capped by the penal sum, simply paying this amount without attempting to complete the contract is usually a last resort and not a standard initial option. The surety's primary obligation is to ensure the project is completed per the contract terms. They will typically choose the most economical of the other options: financing the principal, tendering a new contractor, or taking over the project.

  13. In construction cash flow terminology, what does 'float' refer to?

    Answer: Funds temporarily available because checks issued have not yet cleared

    Float represents the temporary availability of funds resulting from the lag between when a check is issued and when it actually clears the bank.

  14. A construction firm's accounts payable clerk receives an email, seemingly from a regular subcontractor, stating they have switched banks and providing new wire instructions for an upcoming payment. This is a common tactic in which type of cyber-attack?

    Answer: Business Email Compromise (BEC)

    This scenario perfectly describes a Business Email Compromise (BEC) attack. In a BEC scam, attackers impersonate a trusted entity (like a vendor or executive) via email to trick an employee into making an unauthorized financial transaction. This has become an increasingly common and costly threat to the construction industry.

  15. A contractor's cash flow projection shows significant negative cash flow in months 3 and 4 of a 12-month project. What is the most appropriate corrective action?

    Answer: Arrange a short-term line of credit or construction loan to bridge the gap

    Arranging financing such as a revolving credit line before the gap occurs is the appropriate response, ensuring the contractor can meet obligations without disrupting project operations.

  16. A construction company is undertaking a project in an area known for soil instability. During the risk identification phase of the risk management process, what is the most appropriate initial action for the project's financial professional?

    Answer: Document the potential for unforeseen geotechnical issues in a risk register.

    The first step in the risk management process is risk identification. A risk register is a tool used to formally document identified risks. Before any mitigation strategies (like purchasing insurance, allocating funds, or hiring experts) can be properly evaluated and implemented, the risk must first be formally identified and documented.

  17. Under the percentage-of-completion method, contract revenue is recognized based on:

    Answer: Costs incurred to date divided by total estimated costs

    Revenue is recognized proportionally as the ratio of costs incurred to total estimated contract costs, reflecting work actually performed.

  18. In the context of a construction company's safety program, which of the following BEST describes the primary human resources and safety function of a daily "toolbox talk"?

    Answer: To provide brief, site-specific safety training on hazards relevant to the day's work.

    Toolbox talks are short, informal safety meetings conducted at the jobsite before work begins. Their main purpose is to reinforce safety protocols, discuss specific hazards associated with the tasks planned for that day, and keep safety awareness high among the crew.

  19. What financial statement lists assets from current to long term?

    Answer: Balance Sheet

    The balance sheet is a financial statement that lists assets from current to long term. It provides a snapshot of a company's financial position at a specific point in time by showing what the company owns (assets), what it owes (liabilities), and the shareholders' equity. Assets are typically listed in order of liquidity, starting with current assets and moving towards long-term assets. This allows stakeholders to understand the company's financial health and its ability to meet short-term and long-term obligations.

  20. An owner wants to begin a complex industrial project where the full scope is not yet defined, making a fixed price impossible to determine. To minimize risk for the contractor and allow for a fast start, the owner agrees to pay for all labor, materials, and equipment, plus a pre-negotiated amount for the contractor's overhead and profit. Which contract type does this describe?

    Answer: Cost-Plus-Fee

    A Cost-Plus-Fee contract is one where the contractor is reimbursed for all allowable expenses (costs) to perform the work, plus an additional payment (fee) to cover overhead and generate profit. This model is used when the scope is uncertain and places the most risk of cost overruns on the owner, as there is no set ceiling on the final price.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. ccifp.cfma.org — Retake policy, score validity, fees, exam format, passing score, retake fee, score release, test dates, test delivery · verified Oct 2026
  2. pearsonvue.com — Registration deadline · verified Oct 2026