  1. Which financial document is most critical for a construction company seeking a surety bond?

    Answer: CPA-prepared financial statements (reviewed or audited)

    Sureties require CPA-prepared reviewed or audited financial statements to assess the contractor's financial strength and bonding capacity.

  2. The 'backlog' figure reported by construction companies represents:

    Answer: Revenue remaining to be earned on signed contracts

    Backlog is the dollar value of work under contract that has not yet been performed, indicating future revenue pipeline.

  3. In construction, the term 'underbilling' refers to a situation where:

    Answer: The contractor has earned more revenue than it has billed

    Underbilling (costs in excess of billings) occurs when earned revenue based on completion exceeds amounts invoiced, creating a contract asset.

  4. Which ratio measures the relationship between a construction company's total liabilities and its tangible net worth?

    Answer: Leverage ratio (liabilities to net worth)

    The leverage ratio (total liabilities / tangible net worth) is a primary surety underwriting metric indicating how much creditor capital funds operations versus owner equity.

  5. A construction company's 'over/under billing schedule' is used primarily to:

    Answer: Reconcile contract billing status with earned revenue across all projects

    The over/under billing schedule (WIP schedule) compares billed amounts to earned revenue on each project, identifying overbilled and underbilled positions.

  6. When a construction company uses project-specific financing, the lender typically requires the borrower to establish a:

    Answer: Controlled project account with disbursement oversight

    Project-specific lenders require controlled or escrow accounts so disbursements can be monitored and funds are used exclusively for that project.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. ccifp.cfma.org — Retake policy, score validity, fees, exam format, passing score, retake fee, score release, test dates, test delivery · verified Oct 2026
  2. pearsonvue.com — Registration deadline · verified Oct 2026