Retainage in construction contracts is typically released when:
Answer: Substantial completion or final completion is achieved
Retainage (typically 5–10% withheld from each payment) is released upon substantial or final completion and owner acceptance.
Which type of bond guarantees that a construction contractor will complete the project according to contract terms?
Answer: Performance bond
A performance bond protects the project owner by guaranteeing the surety will complete the project if the contractor defaults.
Under the percentage-of-completion method, contract revenue is recognized based on:
Answer: Costs incurred to date divided by total estimated costs
Revenue is recognized proportionally as the ratio of costs incurred to total estimated contract costs, reflecting work actually performed.
A contractor with negative working capital may signal which risk to lenders and sureties?
Answer: Inability to meet short-term obligations
Negative working capital (current liabilities > current assets) indicates the contractor may struggle to pay suppliers, subcontractors, and short-term debts.
In construction project financing, a 'completion guarantee' is typically provided by:
Answer: The general contractor to the lender
A completion guarantee is a contractor's assurance to the lender that the project will be completed regardless of cost overruns, protecting the lender's collateral.
What is the purpose of a joint check agreement in construction financing?
Answer: To ensure payment is made jointly to the contractor and subcontractor/supplier
A joint check agreement directs the owner to make payment checks payable to both the GC and sub/supplier, ensuring funds reach lower-tier parties.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- ccifp.cfma.org — Retake policy, score validity, fees, exam format, passing score, retake fee, score release, test dates, test delivery · verified Oct 2026
- pearsonvue.com — Registration deadline · verified Oct 2026