What does a 'cost baseline' document in project controls, and when is it formally approved?
-
A
It documents the approved time-phased budget and is approved before project execution begins
-
B
It records actual costs incurred and is updated monthly
-
C
It documents contingency reserves and is approved at project close
-
D
It records vendor invoices and is approved by accounts payable