When preparing a cost status update for a client who has limited cost management experience, which approach is MOST appropriate?
-
A
Use full AACE terminology to demonstrate professionalism
-
B
Translate technical cost metrics into business impact language such as budget risk and schedule implications
-
C
Provide only the raw cost data without interpretation
-
D
Defer to the project manager to explain all cost information