An 'overbilled' condition on a construction WIP schedule indicates that:
Select your answer
A
The contractor has billed less than the value of work completed to date
B
The contractor has billed more than the value of work earned based on completion
C
The project is behind the contractual schedule
D
Total costs have exceeded the original contract budget