CCA Construction Cost Principles & Accounting 3 — Questions and Answers
Question 1: Which accounting method is most commonly used by small home builders for tax purposes because it defers income recognition?
- Percentage-of-completion method
- Completed-contract method (Correct answer)
- Cost-recovery method
- Installment sales method
Correct answer: Completed-contract method
The completed-contract method defers all revenue and expense recognition until the contract is substantially complete, providing a tax deferral benefit for qualifying small contractors.
Question 2: A bid bond guarantees that if a contractor is awarded a project, the contractor will:
- Complete the project within the agreed budget
- Enter into the contract and furnish required performance bonds (Correct answer)
- Pay all subcontractors and suppliers promptly
- Correct defects discovered within one year of completion
Correct answer: Enter into the contract and furnish required performance bonds
A bid bond ensures the contractor will execute the contract and provide performance and payment bonds if awarded the project.
Question 3: Front-loading a schedule of values inflates early payment applications by:
- Understating the cost of early work items and overstating later items
- Overstating the cost of early work items and understating later items (Correct answer)
- Evenly distributing costs across all line items
- Shifting costs to change orders rather than base contract work
Correct answer: Overstating the cost of early work items and understating later items
Front-loading assigns higher values to early-schedule line items than their actual cost, enabling the contractor to collect cash in excess of work performed early in the project.
Question 4: An auditor discovers that equipment depreciation charged to a government contract exceeds the actual cost of the equipment over the contract period. This is a violation of which cost principle?
- Reasonableness
- Allocability
- Allowability (Correct answer)
- Consistency
Correct answer: Allowability
Charging depreciation that exceeds actual equipment cost violates allowability because the government cannot be charged more than the asset's actual cost.
Question 5: The formula for calculating cost variance (CV) in earned value management is:
- Planned Value (PV) minus Actual Cost (AC)
- Earned Value (EV) minus Actual Cost (AC) (Correct answer)
- Earned Value (EV) minus Planned Value (PV)
- Actual Cost (AC) minus Budget at Completion (BAC)
Correct answer: Earned Value (EV) minus Actual Cost (AC)
Cost Variance equals Earned Value minus Actual Cost; a negative CV indicates the project is over budget.
Question 6: Which document formally authorizes a contractor to begin work on a change in scope before a change order is fully executed?
- Notice to proceed
- Construction change directive (CCD) (Correct answer)
- Request for information (RFI)
- Architect's supplemental instruction (ASI)
Correct answer: Construction change directive (CCD)
A Construction Change Directive (CCD) directs the contractor to proceed with changed work immediately while the price and time impact are still being negotiated.
Question 7: Under FAR Part 31, which of the following costs is expressly unallowable on government construction contracts?
- Reasonable wages paid to construction workers
- Entertainment costs and lobbying expenses (Correct answer)
- Depreciation on owned construction equipment
- Insurance premiums required by the contract
Correct answer: Entertainment costs and lobbying expenses
FAR Part 31 expressly identifies entertainment and lobbying costs as unallowable charges to government contracts.
Which accounting method is most commonly used by small home builders for tax purposes because it defers income recognition?