Under the percentage-of-completion method, how is revenue recognized on a long-term construction contract?
-
A
Entirely when the project reaches substantial completion
-
B
In proportion to the costs incurred relative to total estimated costs
-
C
Evenly over the contract duration regardless of progress
-
D
Only when the owner issues a certificate of payment