CCA Cheat Sheet 2026
The 30 highest-yield CCA facts, distilled from real exam questions. Print it, save it as a PDF, or study it here — free, no sign-up.
175 questions
180 min time limit
70.00% to pass
- Which overhead allocation base is most appropriate for a labor-intensive construction contractor whose overhead costs are primarily driven by supervision? → Direct labor hours or direct labor cost
- Which document serves as the primary baseline for measuring construction project performance against cost, schedule, and scope? → Performance measurement baseline (PMB)
- What is the first step in the construction audit process? → Audit planning
- Which risk management tool assigns numerical probabilities to potential project risks and calculates an expected monetary value for each? → Quantitative risk analysis (Monte Carlo simulation)
- Under the FAR (Federal Acquisition Regulations), which cost is explicitly unallowable in a government construction contract? → Advertising and public relations costs not related to the contract
- In construction contract auditing, a 'pencil copy' of a pay application refers to: → A preliminary draft submitted for owner/architect review before formal submission
- Which contract type places the most financial risk on the contractor? → Fixed-price contract
- When reviewing change orders during a construction audit, which red flag most warrants further investigation? → A high volume of change orders for work that falls within the original contract scope
- When reviewing construction project schedules, an auditor should be alert to schedule compression techniques that may increase which project risk? → Quality defects and rework costs
- When a construction auditor discovers a material weakness in internal controls, the proper disclosure is to: → Report to senior management and the audit committee or board
- Which insurance type protects an owner against losses arising from contractor-caused property damage during construction? → Contractor's general liability insurance
- An auditor identifies that a subcontractor's invoices consistently lack supporting backup documentation. The best immediate audit step is to: → Issue a formal audit finding and request documentation from the subcontractor
- In construction auditing, 'retainage' refers to: → A portion of each progress payment withheld by the owner until project completion
- Which of the following is an example of a period cost in construction accounting? → Corporate office rent unrelated to any project
- A construction project auditor uses the 50/50 rule for measuring earned value. This means: → 50% credit when work starts, 50% credit at completion
- Which technique involves auditors selecting and confirming a random sample of material deliveries directly with suppliers to detect fictitious charges? → Accounts payable confirmation
- Which of the following best describes 'substantive testing' in a construction audit? → Directly testing account balances and transaction details for completeness and accuracy
- An 'overbilled' condition on a construction WIP schedule indicates that: → The contractor has billed more than the value of work earned based on completion
- In competitive sealed bidding, a 'responsive bid' is one that: → Conforms materially to all requirements of the solicitation document
- A construction auditor reviewing labor records should be alert to employees consistently recording hours just below overtime thresholds, which may indicate: → Manipulation of records to avoid overtime reporting requirements or scrutiny
- A contractor's estimate-at-completion (EAC) exceeds the original contract price. Under GAAP, the contractor must: → Recognize the full anticipated loss immediately in the current period
- Which analytical procedure is most useful for detecting unusual patterns in contractor billing on a long-term project? → Trend analysis comparing monthly billings to project progress curves
- Which method of inventory valuation, when prices are rising, results in the lowest reported net income for a construction materials supplier? → LIFO (Last-In, First-Out)
- Which type of contract clause protects a contractor from absorbing the full cost of extraordinary material price escalation on long-duration projects? → Price escalation or material cost adjustment clause
- Concurrent delay in construction contracting refers to: → Overlapping delays caused by both the owner and the contractor occurring at the same time
- The IIA Code of Ethics requires internal auditors to exhibit which of the following regarding conflicts of interest? → Avoid situations that impair or appear to impair objectivity
- What are direct costs in a construction project? → Project-specific materials and labor
- Which clause in a contract helps manage risk by addressing unexpected delays? → Force majeure clause
- A construction auditor is asked by a senior executive to exclude a significant finding from the audit report to avoid embarrassment. The auditor should: → Refuse and maintain the finding, escalating if necessary
- A construction auditor verifying Davis-Bacon compliance should review: → Certified payroll records (WH-347) for each worker classification
Turn these facts into recall:
Was this helpful?