CCA Cheat Sheet 2026
The 30 highest-yield CCA facts, distilled from real exam questions. Print it, save it as a PDF, or study it here — free, no sign-up.
175 questions
180 min time limit
70.00% to pass
- Which document serves as the primary baseline for measuring construction project performance against cost, schedule, and scope? → Performance measurement baseline (PMB)
- What is the first step in the construction audit process? → Audit planning
- In construction contract auditing, a 'pencil copy' of a pay application refers to: → A preliminary draft submitted for owner/architect review before formal submission
- Which contract type places the most financial risk on the contractor? → Fixed-price contract
- When reviewing construction project schedules, an auditor should be alert to schedule compression techniques that may increase which project risk? → Quality defects and rework costs
- In construction auditing, 'retainage' refers to: → A portion of each progress payment withheld by the owner until project completion
- A construction project auditor uses the 50/50 rule for measuring earned value. This means: → 50% credit when work starts, 50% credit at completion
- Which technique involves auditors selecting and confirming a random sample of material deliveries directly with suppliers to detect fictitious charges? → Accounts payable confirmation
- Which of the following best describes 'substantive testing' in a construction audit? → Directly testing account balances and transaction details for completeness and accuracy
- An 'overbilled' condition on a construction WIP schedule indicates that: → The contractor has billed more than the value of work earned based on completion
- In competitive sealed bidding, a 'responsive bid' is one that: → Conforms materially to all requirements of the solicitation document
- A construction auditor reviewing labor records should be alert to employees consistently recording hours just below overtime thresholds, which may indicate: → Manipulation of records to avoid overtime reporting requirements or scrutiny
- Concurrent delay in construction contracting refers to: → Overlapping delays caused by both the owner and the contractor occurring at the same time
- What are direct costs in a construction project? → Project-specific materials and labor
- Which clause in a contract helps manage risk by addressing unexpected delays? → Force majeure clause
- A construction auditor verifying Davis-Bacon compliance should review: → Certified payroll records (WH-347) for each worker classification
- Which control document is the primary tool for tracking actual versus budgeted costs at the work package level on a construction project? → Cost Control Report (CCR)
- How are retainage amounts typically treated in construction accounting? → Recorded as a liability until paid
- During a construction audit, an auditor verifies that project financial reports reconcile to the general ledger. This procedure addresses which assertion? → Accuracy and existence
- What is the auditor's primary concern when reviewing a construction project's contingency drawdown process? → Contingency is used only for unforeseen costs, not known scope additions
- Under the percentage-of-completion method in construction accounting, revenue is recognized based on: → The proportion of contract costs incurred to date relative to total estimated costs
- Which condition in a subcontract most effectively protects the owner's right to audit subcontractor records? → An explicit audit rights clause granting the owner access to subcontractor cost records
- Which red flag suggests that a contractor may be using change orders to recover costs that should have been included in the original bid? → A high volume of change orders for items that were reasonably foreseeable at bid time
- Which change order pricing method is most auditable and transparent for a cost-plus construction contract? → Force account (time and material) with daily records signed by both parties
- Which element of an effective construction fraud prevention program includes training field staff to recognize and report suspicious activity? → Anti-fraud awareness and ethics training with a confidential hotline
- Which type of evidence provides the highest audit reliability? → External documentation
- A CCA auditor finds that change orders consistently increase scope but the project schedule was never formally updated. What risk does this create? → Inability to accurately assess contractor time extension entitlements or delay damages
- A construction auditor reviewing payroll records finds that 15 workers have the same home address listed on their W-4 forms. This is most consistent with: → Ghost employee payroll fraud using a single address to collect multiple paychecks
- In construction auditing, 'three-way matching' in the procurement cycle refers to matching which three documents? → Purchase order, receiving report, and vendor invoice
- What does a Guaranteed Maximum Price (GMP) contract include? → Cost plus with a price cap
Turn these facts into recall: